2、
Fasten the floor starter to the perforated keel with screws.
3、
Place the flooring intermediates between the slots of the two pieces of flooring and keep all the intermediates in a straight line
4、
Lock the intermediate pieces with screws and install the flooring sequentially in this way until the last piece.
5、
When installing the last floor, the same as the first floor.
caveat
1、
Requires a level and solid foundation
2、
Appropriate gaps need to be left around the flooring for thermal expansion of the flooring.
3、
For floor joints, 2 keels are required to ensure that the floor is firmly fixed to the keel.
4、
For better locking of the floor, the pre-drilled diameter of the screws must be smaller than the diameter of the screws.
5、
In order to have a better paving result, please inform the specifics of the construction project in advance.