With the rapid development of urban rail transit projects, the U-Beam is widely used on viaduct roads. Currently, U girder is one of the most innovative viaducts used in urban rail transportation. It has the advantages of noise reduction, low building height, high space utilization, and good appearance. With the advancement of technology, construction methods have changed from cast-in-place to precast hoisting. Use either double crane lifting or gantry crane lifting to hoist the U girder.
Our key projects
Boyoun is a professional enterprise that designs and manufactures U-Beam formworks. The U-Beam has been successfully applied to Shanghai Urban Rail Transit, Qingdao Intercity Rail, Pakistan Light Rail, Dubai Light Rail, etc.
Specification
Precast U girder formwork structure: outer side formwork, inner formwork, bottom formwork, support lead screw, jack, work platform, Vibrator, crawling ladder, blanking plate, etc.
- Product Details
- {{item.text}}
Quick Details
-
Application:
-
Courtyard
-
Design Style:
-
Industrial
-
Type:
-
steel formwork, Recyclable
-
Place of Origin:
-
Shandong, China
-
Brand Name:
-
Boyoun
-
Material:
-
Q235 Steel
-
Usage:
-
Concorete Formwork
-
Size:
-
Customizable
-
Feature:
-
Easily Assembled
Quick Details
-
Warranty:
-
5 years
-
After-sale Service:
-
Online technical support, Onsite Installation, Onsite Training, Onsite Inspection, Other
-
Project Solution Capability:
-
graphic design, 3D model design, total solution for projects
-
Application:
-
Courtyard
-
Design Style:
-
Industrial
-
Type:
-
steel formwork, Recyclable
-
Place of Origin:
-
Shandong, China
-
Brand Name:
-
Boyoun
-
Material:
-
Q235 Steel
-
Usage:
-
Concorete Formwork
-
Size:
-
Customizable
-
Feature:
-
Easily Assembled
PRODUCT DESCRIPTION
Precast U-girder formwork
Precast U-girder formwork
|
|
|
|
|
||||
1
|
Material
|
Q235B, Q355Steel.
|
|
|
||||
2
|
Design time
|
The preliminary technical plan design will take 3 days.
|
|
|
||||
|
|
The fabrication drawings will take 5 days to design.
|
|
|
||||
3
|
Fabrication
|
The normal duration is about 40 days.
|
|
|
||||
4
|
Painting
|
Each formwork is painted three times: a primer, a middle paint, and a top paint. This prevents rust from corroding the formwork.
|
|
|
||||
5
|
Delivery
|
Boyoun maintains positive relationships with many logistics companies to ensure prompt delivery of formworks to the port.
|
|
|
||||
6
|
Installation on Project site
|
Boyoun can assign one or two engineers to provide technical support at the project site.
|
|
|
WHY CHOOSE US
Advantages
1. The inner formwork is fixed by the cross beam and the external formwork. The upper part uses jackscrews to adjust and fix the position of the inner formwork. The inner formwork is retracted and supported as a whole through hydraulic cylinders. It has a high degree of automation, shortens the construction period, and improves construction efficiency.
2. The outer formwork is connected to the hinge axis on the ground. Through the shoulder top and the support screw device, the outer formwork can be opened and closed as a whole. The operation is simple and greatly protects the U-beam from being scratched when lifting it.
3. Rubber strips are used to seal the outer formwork, inner formwork, and bottom formwork to prevent any leaks of slurry.
4. The vibrators are arranged crosswise inside and outside to enhance the compactness and appearance quality of the concrete.
Successful Cases
Malaysia LRT3 Project
RELATED PRODUCTS
COMPANY PROFILE
Introduction of Shandong Boyoun Industries Co., Ltd.
Boyoun was founded in Beijing in 2006 and its headquarters are located in Binzhou Industrial Park in Shandong Province. Boyoun has over 400 employees, with over 40% being technical engineers. Boyoun focuses on Bridge formwork R&D, Production, Rental, and technical services,which is a national hign-tech enterprise. The production base with a area of 100000㎡.The capacity of infrastructure equipment is 100 thousand tons.We have opened up emerging markets represented by Southeast Asia, Russia, Africa and the Middle East, and laid out in advance to contribute to the national “One Belt, One Road” strategic concept.
Painting Workshop
Ready for Painting
Welding Workshop
CERTIFICATIONS AND HONORS
DELIVERY
FAQ
Q1: Are you trading company or manufacturer?
A: We are
manufacturer, o
ur factory is in Binzhou, Shandong, China
Q2: Do you provide engineer service?
A: Yes, we could make the detail proposal as project drawing free. For construction site service need some charge for cost.
Q3. How fast can my order be delivered?
You can state your desired Delivery date for your order. The order and the desired delivery date will be checked after your order got sent. When you receive your order confirmation, you will find the information on your final delivery date (outgoing). We will, of course, try our best to meet the specified delivery date.
Q4. What's the material of your products?
Steel Q235B or Q355B.
Q2: Do you provide engineer service?
A: Yes, we could make the detail proposal as project drawing free. For construction site service need some charge for cost.
Q3. How fast can my order be delivered?
You can state your desired Delivery date for your order. The order and the desired delivery date will be checked after your order got sent. When you receive your order confirmation, you will find the information on your final delivery date (outgoing). We will, of course, try our best to meet the specified delivery date.
Q4. What's the material of your products?
Steel Q235B or Q355B.
Hot Searches